Los Angeles ADU permit requirements

Last reviewed: June 22, 2026

Quick answer

Permitting an accessory dwelling unit (ADU) in Los Angeles, California means pulling a building permit from the local authority that issues it. ArchPermit tracks 19 source-cited requirements (9 required, the rest conditional) for this jurisdiction. Submittals go through ePlanLA (Electronic Plan Review LA). These requirements were last reviewed June 22, 2026; confirm the exact forms and fees with the local permitting authority.

A source-cited checklist of what an ADU (accessory dwelling unit) permit package needs in City of Los Angeles. Every item links to its authoritative source; items that vary are flagged to confirm locally.

ADUs are approved ministerially (no discretionary review or hearing). LA's local ADU/JADU/Movable-Tiny-House standards are in Ordinance 186,481 / LAMC § 12.22 A.33; current code basis is the 2023 LA Building/Residential Codes. LADBS runs an ADU Standard Plan Program: choosing a pre-approved standard plan reduces the submittal to a title sheet, plot plan, and a copy of the approved plan. Plan-check applications expire 18 months from submittal.

  • Architectural Plans (floor, roof, elevations, sections)required

    Dimensioned floor plans (room sizes/uses), roof plan, exterior elevations, and cross-sections. Required for a custom (non-standard-plan) ADU.

    source · reviewed 2026-06-22
  • Building Permit Application (signed)required

    Application signed by the owner or a licensed contractor/authorized agent. Owner-builder requires a notarized/in-person signature; a contractor must show workers'-comp coverage, a state license, and LA business-tax registration.

    source · reviewed 2026-06-22
  • CALGreen / Green Building Forms (GRN set)required

    Mandatory CALGreen Requirements Checklist (Form GRN 4) plus the green-building form set (e.g. GRN 1/11/14/16) incorporated into the plans.

    source · reviewed 2026-06-22
  • Material Specificationsrequired

    Material specifications for the structure, submitted as part of the document package.

    source · reviewed 2026-06-22
  • Plot / Site Plan (to scale)required

    Fully dimensioned plot plan showing property lines, front/side/rear setbacks, separation between the ADU and the primary dwelling, drainage, north arrow, ADU dimensions/area, driveways, and parking.

    source · reviewed 2026-06-22
  • Plumbing / Mechanical / Electrical Plansrequired

    Plans showing HVAC equipment location & BTU output, plumbing fixture locations/dimensions, and electrical outlets, panels, and smoke detectors.

    source · reviewed 2026-06-22
  • Structural Plans (foundation, framing, details)required

    Foundation plan, floor/roof framing plans, truss plans, and structural framing/connection details (shear walls, holdowns, footings).

    source · reviewed 2026-06-22
  • Title 24 Energy Compliance (calcs + CF-1R / MF-1R + certs)required

    Energy calculations and Title 24 forms (CF-1R, MF-1R, CF-GR, Insulation Certificate) from an Energy-Commission-approved program (Climate Zone 9), attached to the plans; HERS field verification as noted.

    source · reviewed 2026-06-22
  • Title Sheet & Area Calculationsrequired

    Cover sheet with the sheet index, vicinity map, floor-area calculations (Zoning/Building/School District), APN, legal description, zone, lot area, parking, fire-sprinkler info, and owner/applicant info.

    source · reviewed 2026-06-22
  • ADU-Conversion Documentationconditional

    When converting an existing, detached, or unpermitted structure to an ADU/JADU, follow the additional submittal standards in Information Bulletin P/BC 2023-150.

    source · reviewed 2026-06-22
  • Approved ADU Standard Plan (copy)conditional

    A complete copy of the LADBS-approved ADU Standard Plan drawings. Required only when using the Standard Plan Program path (in which case the custom plan sheets below are not needed).

    source · reviewed 2026-06-22
  • Architect / Engineer Wet Signature & Stampconditional

    CA-licensed architect/engineer signature and wet stamp on each plan sheet. Exempt: a one-story wood-frame ADU designed per IB P/BC 2023-004.

    source · reviewed 2026-06-22
  • Department Clearances (Clearance Summary Worksheet)conditional

    Clearances from other departments per the attached Clearance Summary Worksheet (e.g. Fire, City Planning/Zoning, DWP easements, Coastal). Varies by site.

    source · reviewed 2026-06-22
  • Grading Plans / Grading Pre-Inspectionconditional

    Grading plans and a grading pre-inspection report where grading is involved; a separate grading application may be required.

    source · reviewed 2026-06-22
  • JADU Recorded Covenant / Deed Restrictionconditional

    For a Junior ADU only: a recorded 'Covenant and Agreement Regarding Junior Accessory Dwelling Unit' (owner-occupancy, one per lot, no separate sale), approved by LADBS before recording.

    source · reviewed 2026-06-22
  • Soils / Foundation / Geology Reportconditional

    When required by site conditions, soils/foundation/geology report(s) must be approved by the LADBS Grading Section (per IB P/BC 2023-113 / 2023-116); the approval letter becomes part of the plans.

    source · reviewed 2026-06-22
  • Solar PV / Future Solar Zoneconditionalverify locally

    The LADBS ADU page states detached new-construction ADUs 'must have solar panels,' and the submittal bulletin lists a 'future solar zone.' The exact documentation and exemptions vary, so confirm applicability per project before relying on it.

    source · reviewed 2026-06-22
  • Stormwater / LID Plan (LA Sanitation)conditional

    A Low Impact Development stormwater plan cleared by LA Sanitation, where applicable.

    source · reviewed 2026-06-22
  • Structural Calculationsconditional

    Complete vertical + lateral load calculations signed by a CA-licensed architect/engineer. Exempt: a one-story wood-frame ADU designed per the Wood Frame Prescriptive Provisions (IB P/BC 2023-004).

    source · reviewed 2026-06-22

Los Angeles ADU permit questions

Do I need a permit to build an ADU in Los Angeles?
Yes. An accessory dwelling unit (ADU) in Los Angeles requires a building permit. ArchPermit tracks 19 cited requirements for this jurisdiction (9 required, the rest conditional). Always confirm the exact forms, fees, and code edition with the local permitting authority that issues the permit.
What does an ADU permit package require in Los Angeles?
Core required items include: Architectural Plans (floor, roof, elevations, sections); Building Permit Application (signed); CALGreen / Green Building Forms (GRN set); Material Specifications; Plot / Site Plan (to scale); Plumbing / Mechanical / Electrical Plans, plus 3 more. Each requirement links to its authoritative source, and nothing is permit-ready until an independent licensed professional reviews and seals it.
How are ADU permits submitted in Los Angeles?
Los Angeles accepts permit submittals via ePlanLA (Electronic Plan Review LA). ArchPermit prepares a draft package you can submit there after a licensed architect reviews and seals it.