Denver ADU permit requirements
Last reviewed: June 22, 2026
Quick answer
Permitting an accessory dwelling unit (ADU) in Denver, Colorado means pulling a building permit from the local authority that issues it. ArchPermit tracks 18 source-cited requirements (14 required, the rest conditional) for this jurisdiction. Submittals go through Denver E-Permits (Accela) online portal. These requirements were last reviewed June 22, 2026; confirm the exact forms and fees with the local permitting authority.
A source-cited checklist of what an ADU (accessory dwelling unit) permit package needs in City and County of Denver. Every item links to its authoritative source; items that vary are flagged to confirm locally.
A new ADU requires three concurrent permits reviewed by CPD's Residential Review Team: a Zoning permit, a Building permit, and a Sewer Use & Drainage Permit (SUDP); the property's zone district must already allow ADUs or be rezoned first. Denver implements Colorado's HB24-1152 (effective Dec 16 2024), which requires ADUs to be allowed in all residential districts and relaxes owner-occupancy. An address must be assigned before applying.
- Architectural Drawingsrequired
Drawings accurately showing the scope and meeting health, safety, egress, fire, and structural code, with construction-document basics: address, legal description, design contact, seals/signatures, scope narrative, adopted-code list, scale/north arrow/legend.
source · reviewed 2026-06-22 - Building Code Data Table + Gross Floor Area (GFA) Tablerequired
Climatic/geographic design criteria and the GFA of each floor of every building including basements; GFA drives affordable-housing and permit fees.
source · reviewed 2026-06-22 - Building Sectionsrequired
Building volume and components: foundation type, structural members, attic volume/ventilation, stairs/ramps, windows/doors, space uses, and ceiling heights.
source · reviewed 2026-06-22 - Denver Energy Code Documents (checklist + Manuals J/S/D)required
Completed Denver Energy Code Residential Compliance Checklist; ACCA Manual J, S, and D for new HVAC; plus the report for the chosen compliance pathway (REScheck / energy model / ERI).
source · reviewed 2026-06-22 - Details / Enlarged Drawingsrequired
Detail drawings for wall sections (member sizes, R-values, fire blocking, sheathing, finishes), foundation, roof, stairs, and site/retaining walls.
source · reviewed 2026-06-22 - Exterior Elevationsrequired
All existing + proposed structures, finished grade, overhang dimensions, fire-rated-wall opening analysis, height in feet/stories, bulk planes, upper-story setback/stepback, and rooftop mechanical screening.
source · reviewed 2026-06-22 - Floor Plans / Reflected Ceiling Plansrequired
Room uses, kitchens (full vs partial), plumbing fixtures, fire-rated walls/separations, ceiling height, egress path, emergency escape & rescue openings, glazing, ventilation, radon vent, and smoke/CO alarms.
source · reviewed 2026-06-22 - Geotechnical Soils Reportrequired
A current soils report is required for new dwellings and conditioned accessory structures (which includes a new ADU), plus excavation and expansive-soil cases.
source · reviewed 2026-06-22 - Roof Planrequired
Attic ventilation calc, skylights/U-values, drainage, roof overhangs (with fire rating if within 5 ft of a line), roof slope, solar-ready zone, and radon-vent termination.
source · reviewed 2026-06-22 - Sewer Use & Drainage Permit (SUDP) Submittalrequired
All development is reviewed by the SUDP team for sanitary, storm/grading, floodplain, groundwater, and ROW impacts; new ADU living space requires a SUDP.
source · reviewed 2026-06-22 - Site Planrequired
Scaled plan dimensioning zone-lot lines, abutting streets/alleys/sidewalks, existing + proposed structures, driveways, setbacks, the 65/35 zone-lot depth line, spot grades, and tree/parkway details.
source · reviewed 2026-06-22 - Structural Drawings & Calculationsrequired
Complete load path to the foundation: load info, material strengths, foundation plans + reinforcement, framing plans, and calculations for all non-prescriptive elements.
source · reviewed 2026-06-22 - Survey (Boundary / Land Survey / Improvement Survey Plat)required
Required for a new dwelling on vacant land; an Improvement Survey Plat is required for additions when a proposed exterior wall is within 3 ft of a lot line. ILCs are not accepted where a survey is required.
source · reviewed 2026-06-22 - Zoning Code Data Tablerequired
Zone district/overlays, building form and use of each structure, zone-lot area, and building coverage; for an attached ADU, must list the GFA used as the ADU.
source · reviewed 2026-06-22 - Address Assignmentconditional
Must be requested before permit application when adding a new dwelling unit, including attached or detached ADUs.
source · reviewed 2026-06-22 - Excavation / Shoring Documentsconditional
DRC structures require an excavation permit (issued separately) unless an exception applies; may require excavation plans, engineer-stamped shoring, soils report, and adjacent-owner affidavits.
source · reviewed 2026-06-22 - Landmark Certificate of Appropriateness (COA)conditional
Required before building/zoning permit approval if the property is a designated landmark or in a historic district.
source · reviewed 2026-06-22 - Owner-Occupancy Documentation (ADU in a Single-Unit zone)conditional
Required when building an ADU in a Single-Unit zone district (except when built at the same time as the primary dwelling); submitted only when requested.
source · reviewed 2026-06-22