Indianapolis ADU permit requirements

Last reviewed: June 22, 2026

Quick answer

Permitting an accessory dwelling unit (ADU) in Indianapolis, Indiana means pulling a building permit from the local authority that issues it. ArchPermit tracks 15 source-cited requirements (9 required, the rest conditional) for this jurisdiction. Submittals go through Accela Citizen Access (DBNS). These requirements were last reviewed June 22, 2026; confirm the exact forms and fees with the local permitting authority.

A source-cited checklist of what an ADU (accessory dwelling unit) permit package needs in Indianapolis. Every item links to its authoritative source; items that vary are flagged to confirm locally.

In Indianapolis–Marion County zoning an ADU is a 'Secondary Dwelling Unit' (SDU), an accessory use ('A') permitted by-right in the dwelling districts where the use table marks it (a variance is needed only if a development standard isn't met), subject to Section 06.EE: one SDU per lot, owner-occupancy of either the primary or secondary unit (so both can't be rentals), a separate entrance, and one additional off-street parking space. A detached SDU is permitted as a New Accessory Structure and typically needs an Improvement Location Permit + Structural Permit + Drainage Permit. Confirm the current size/district limits against the live ordinance (the 2016 figure of 720 sf may be amended).

  • Building Elevations (all four sides)required

    Elevation drawings of all sides of the existing or proposed structure.

    source · reviewed 2026-06-22
  • Floor Plan(s) with Legendrequired

    For all floors in scope; legend indicating proposed work, rooms labeled with existing/proposed use, smoke-detector locations, and all doors/windows.

    source · reviewed 2026-06-22
  • Foundation Planrequired

    Complete foundation plan for the new accessory structure.

    source · reviewed 2026-06-22
  • Residential Development Application or Class 2 Structural Permit Applicationrequired

    The Residential Development Application (when an Improvement Location Permit is required, e.g. a new detached ADU) and the Class 2 (Residential) Structural Permit Application, completed and signed.

    source · reviewed 2026-06-22
  • Residential Plan Submittal Checklist (completed)required

    The DBNS checklist itself, completed and submitted with the application to confirm the minimum submittal items.

    source · reviewed 2026-06-22
  • Site Plan / Plot Planrequired

    Drawn to 1"=30' (or 1"=40' for large lots): north arrow, lot/subdivision or metes-and-bounds, all existing/proposed structures, setback distances to all property lines, driveway, easements, and septic-tank location if applicable.

    source · reviewed 2026-06-22
  • Two (2) Complete Sets of Plans (to scale)required

    All documents drawn to a standard engineer or architect scale; two full sets with scale, property address, and date shown.

    source · reviewed 2026-06-22
  • Wall Cross-Section (roof system to foundation)required

    Full section labeling all construction elements; one section per distinct wall type (a 'typical' section is not sufficient).

    source · reviewed 2026-06-22
  • Window & Door Framing Detailsrequired

    Framing details for windows and doors.

    source · reviewed 2026-06-22
  • Certificate of Appropriateness (IHPC) + Stamped Plansconditional

    Required if the property is in a historic district and exterior work is performed (Indianapolis Historic Preservation Commission).

    source · reviewed 2026-06-22
  • Egress Windows Labeled in Bedroomsconditional

    Egress windows must be labeled in all bedrooms (any ADU with sleeping rooms).

    source · reviewed 2026-06-22
  • Energy Code Compliance Report (REScheck / software)conditional

    A REScheck report (Total UA Alternative) or a software report (Performance pathway); the prescriptive pathway needs no separate report.

    source · reviewed 2026-06-22
  • Engineer-Sealed Truss Specificationsconditional

    A sealed, engineered roof-truss packet required if engineered trusses are used.

    source · reviewed 2026-06-22
  • Sewer Connection Permit (Citizens Energy Group)conditional

    Required for new construction connecting to sewer; must be obtained before the Structural permit issues (external agency).

    source · reviewed 2026-06-22
  • Statement of Intent and Understandingconditional

    Required only if the property owner (not a licensed contractor) is performing/pulling the permit.

    source · reviewed 2026-06-22