Austin ADU permit requirements

Last reviewed: June 22, 2026

Quick answer

Permitting an accessory dwelling unit (ADU) in Austin, Texas means pulling a building permit from the local authority that issues it. ArchPermit tracks 13 source-cited requirements (7 required, the rest conditional) for this jurisdiction. Submittals go through Austin Build + Connect (AB+C) online portal. These requirements were last reviewed June 22, 2026; confirm the exact forms and fees with the local permitting authority.

A source-cited checklist of what an ADU (accessory dwelling unit) permit package needs in City of Austin. Every item links to its authoritative source; items that vary are flagged to confirm locally.

Under Austin's HOME initiative (Phase 1, effective Feb 5 2024) up to 3 housing units are allowed on an SF-1/SF-2/SF-3 lot (min lot area 5,750 sf); ADU / 2-unit / 3-unit projects go through the standard residential building-permit track (DSD Residential Plan Review). Each new unit needs a unique address requested in advance. A site plan is NOT required for buildings with two or fewer units; a 3-unit project does require one. Whether the permit is by-right/ministerial is not stated on the official pages — confirm with DSD.

  • Austin Energy Building Service Plan Application (BSPA)required

    Required for new dwelling units; Austin Energy reviews concurrent with plan review.

    source · reviewed 2026-06-22
  • Elevation Plansrequired

    Exterior elevations showing structure height and the points of measurement.

    source · reviewed 2026-06-22
  • Existing & Proposed Floor Plansrequired

    To scale, with dimensions, ceiling heights, and room labels.

    source · reviewed 2026-06-22
  • Plot Plan / Site Plan / Survey (to scale)required

    Property lines, setbacks, easements, building lines, flatwork/driveways/sidewalks, roof overhangs, parking spaces with dimensions, and trees ≥19" diameter (including adjacent).

    source · reviewed 2026-06-22
  • Residential New Construction & Addition Permit Applicationrequired

    The core completed application form, signed by the owner and applicant; used for ADU / 2-unit / 3-unit projects.

    source · reviewed 2026-06-22
  • Structural Plans (foundation, framing, brace-wall)required

    Foundation plan sealed by a licensed engineer; framing and brace-wall plans designed by a licensed engineer or architect.

    source · reviewed 2026-06-22
  • Unique Address Assignmentrequired

    Each new dwelling unit must have a unique address/building number, requested from Address Management Services before applying.

    source · reviewed 2026-06-22
  • Acknowledgment of Expired Permitsconditional

    Required to resolve any expired permits shown on AB+C for the property (even prior owners') before intake.

    source · reviewed 2026-06-22
  • Austin Water Service Plan Verification (WWWSPV)conditional

    As applicable — required when water demand increases or a new dwelling unit is proposed; stamped by Austin Water.

    source · reviewed 2026-06-22
  • Demolition Permit Applicationconditional

    As applicable — required if any portion of an existing exterior wall, roof, or deck is removed; total demolitions are filed separately.

    source · reviewed 2026-06-22
  • Owner's Authorization Letterconditional

    Required when the application is not signed by the property owner.

    source · reviewed 2026-06-22
  • Request for Modification / AMOC (triplex)conditional

    Required for a triplex (single building, 3 attached units) under HOME; not required for other 3-unit configurations.

    source · reviewed 2026-06-22
  • Site Plan (3-unit projects only)conditional

    A site plan is not required for two or fewer units; a 3-unit project requires a separate site-plan submittal.

    source · reviewed 2026-06-22